By Mariyam Umna Ismail

The second phase of K. Himmafushi harbour development project has been completed.

The project was contracted to MTCC by the government in 2019 and was completed on September 30.

Under the project worth MVR 30.5 million:

  • An area of 19,895 cubic meters was dug

  • Dredging of 9,900 cubic meters

  • 251 metres of inner breakwater and 15 metres outer breakwater

  • Concrete pavement constructed in an area of 1,443 square metres

  • A 25-metre-long bridge and a 63-metre wide jetty were constructed

  • Installation of navigation lights and harbour lights

MTCC said in a statement on Friday that with the new harbour in Himmafushi, tourism in the island is progressing. With the guesthouse business, the fishing industry has also expanded, said MTCC.

MTCC said that with the new harbour, it will be easier for the people. The company said that the harbour has enough capacity and space to cater to the increasing number of vessels in the island.

"Therefore, the development and completion of the harbour is an important project that will benefit the people of Himmafushi," the statement read. 