Land reclamation at Thilafushi. (Photo/Urbanco)

Second phase of Thilafushi land reclamation begins

Under the project, work has started on Areas A, B, E and F of the second phase of dredging.

17 September 2023

The second phase of land reclamation at the industrial island of K. Thilafushi began on Thursday, Urbanco said on Sunday.

Under the project, work has started on Areas A, B, E and F of the second phase of dredging.

Urbanco, which contracted China Harbour Engineering Company, began dredging Area B on Thursday.

Under the second phase, dredging will be carried out:

  • Area A - 71.5 hectares

  • Area B - 39.6 hectares

  • Area E - 5.9 hectares

  • Area F - 0.73 ha

Urbanco said in a statement on Sunday that the land is being dredged and developed as part of its efforts to transform Thilafushi into an industrial hub in the Male region.

The project will boost Maldives' industrial activities, Urbanco said. The company also said that the relocation of industrial activities from Male to Thilafushi will reduce the adverse impacts on the environment.

  • Under the master plan, large plots of land will be allocated for various industrial works

  • Once the Thilamale Bridge, which is being constructed through an Indian loan, links Male, Villimale, Thilafushi and Gulhifalhu, it will boost business and industries in the region