Shore protection of Addu Hithadhoo begins

The project was awarded to MTCC on November 25, 2021 for MVR 11.6 million, to be completed within 165 days.

5 October 2022

By Ahmed Mizyal

Shore protection in Addu Hithadhoo began on Wednesday. 

Planning minister Mohamed Aslam inaugurated the project at a ceremony held in Addu.

The project includes:

  • Shore protection of 570 meters on west side of Hithadhoo

  • Deepening of area of 15×50 metres

  • Designated area for swimming

  • A 100-metre breakwater with rocks

The project was awarded to MTCC on November 25, 2021 for MVR 11.6 million, to be completed within 165 days.