Ahmed Mizyal
At a time when a number of projects are being awarded one after the other, MTCC has been tasked with the development of the ports of B. Dharavandhoo and R. Dhuvaafaru.
Agreements for the projects were signed at a ceremony held at the planning ministry Wednesday afternoon by:
-
Adam Azim, CEO of MTCC
-
Fathimat Shana Farooq, Director General, Ministry of Planning
Dhuvaafaru Port Project:
-
Price - MVR 11.4 million
-
Deadline given for completion - 180 days
Dharavandhoo Port Project:
-
Price - MVR 59.9 million
-
Deadline given for completion - 365 days